A water shut off to the 30th through 55th floors, to accommodate the Loop Project Repairs, will be needed Monday April 22nd, between 9am and 5pm. Although the goal was to attempt to finish in two days, demands of the work underway prevented them from completing everything necessary by 5pm on Thursday April 18th. Barring unforeseen conditions or complications, the shut off on Monday April 22nd is expect to be the last for the duration of the project.
55th Floor New line Prep & Test – Thru Friday April 26th
30 to 55th Floor WATER SHUTOFFS Wednesday 22nd 9am to 5pm
55th Floor Demo Old Plumbing – Monday April 22nd thru Friday April 26th
55th Floor Insulation Work – Wednesday April 24th thru Tuesday April 30th
55th Floor Reconstruction – Monday April 29th thru Friday May 17th
If you have any questions, feel free to e-mail us at parktowercondo@draperandkramer.com or give us a call at 773-769-3250.
Get regular updates and other business news, announcements and notices by joining the Park Tower Condo Association e-mail group. Just e-mail us a request to add you!
The water shut off to the 30th through 55th floors, to accommodate the Loop Project Repairs, was delayed. As of now, we expect it to be delayed by one week. It was confirmed conditions are such, additional preparations are required before we can proceed.
We realize residents were anticipating the shut off to occur on April 10th, 11th and 12th, and we apologize for any inconvenience or frustration this delay may have caused.
At present, they believe with more certainty, the shut offs will be Wednesday and Thursday, April 17th and 18th, and their goal is to have all the work done those two days. There WILL NOT be a shut off planned for Friday April 19th. If another shut off is needed, an announcement will go out for Monday April 22nd, or thereafter.
The “Upper Loop Project” is our effort replacing the main plumbing lines valves, which feed cold and hot water Risers serving the 30th to 55th floors. Most of the work is being done above the 55th floor hallway ceiling, and in the crawlspace above the 55th floor.
Following is the remaining anticipated schedule:
55th Floor New line Prep & Test – Monday April 8th thru Friday April 19th
30 to 55th Floor WATER SHUTOFFS Wednesday April 17th, 18th 9am to 5pm
55th Floor Demo Old Plumbing – Monday April 22nd thru Friday April 26th
55th Floor Insulation Work – Wednesday April 24th thru Tuesday April 30th
55th Floor Reconstruction – Monday April 29th thru Friday May 17th
The water shut off to the 30th through 55th floors, to accommodate the Loop Project Repairs, will be delayed. As of now, we expect it to be delayed by one week.
It was confirmed conditions are such, additional preparations are required before we can proceed. We realize residents were anticipating the shut off to occur today, Thursday and Friday, and we apologize for any inconvenience or frustration this delay may cause.
At present, they believe with more certainty, the shut offs will be Wednesday, Thursday, April 17th and 18th, and there goal is to have all the work done those two days. There WILL NOT be a shut off planned for Friday April 19th. If another shut off is needed, an announcement will go out for Monday April 22nd, or thereafter.
We did know it was possible this shut off would not occur, and our apologies if anyone made plans to accommodate. We greatly appreciate everyone’s patience and understanding, as we continue to make this improvement to PT’s plumbing.
Feel free to e-mail with any questions, parktowercondo@draperandkramer.com, or give us a call 773-769-3250.
Water Shutoffs to accommodate work needed to the connections to lines being run for the Upper Loop Project are expected to occur this week as anticipated, Wednesday thru Friday April 10th, 11th and 12th.
These shut offs will effect both HOT and COLD water, from the 30th to 55th floors, 9am to 5pm.
Conditions could change between now and then, which may require them to refine the exact timing, but once we know with more certainty, a final notice will be distributed.
Monday March 25th
The project to replace the main water lines serving the High Zone hot and cold water risers (which provide water to the 30th to 55th floors), has been scheduled to begin on Monday March 25th, and work is anticipated to follow the outline below. Workers are expected to conduct this work in the hallway and the crawlspace above the 55th floor from March 25th through Friday May 9th. They will begin by 9am each weekday and plan to wrap up work by 5pm, though workers anticipate mobilizing around the 8am hour to gear up and make preparations.
55th Floor Ceiling Demo – Monday March 25th thru Friday March 29th
55th Floor Prep and Plumbing – Monday April 1st thru Friday April 5th
55th Floor New line Prep & Test – Monday April 8th thru Friday April 12th
30 to 55th Floor WATER SHUTOFFS Wednesday April 10th, 11th and 12th 9am to 5pm
55th Floor Demo Old Plumbing – Monday April 15th thru Friday April 19th
55th Floor Insulation Work – Wednesday April 17th thru Tuesday April 23rd
55th Floor Reconstruction – Monday April 22nd thru Friday May 10th
From time to time, workers, tools, hallway obstructions, noise, dust and other conditions which could cause some frustration and inconvenience will be present. The noise may be heard downward several floors, particularly during the “Demo” work, and especially the demo of old plumbing. We appreciate all our residents’ patience and understanding while this work is underway.
Units 5501, 5506 and 5511 will need to be accessed during the project (as scheduled above), for access and work on the valves to the main lines above the entryway ceiling. That is the bad news – the good news is, as a part of the project, these valves are being relocated to the hallway. That will decrease the need for access from in or above these units in the future.
Contact the office at 773-769-3250, or e-mail us at parktowercondo@draperandkramer.com with any questions or concerns.