Following is a tentative schedule, with key dates and activities in conjunction with each Riser; please note these are subject to change. Residents and Owners should watch for formal letters, notices and project calendars, which are issued once our team gets plans laid out and in place for work to commence:
’07 and ’08 Bathrooms from the 30th to 55th Floors
Work Begins Monday May 18th 2020 – Major Completion Thursday July 2nd 2020
Initial Notice – The Week of March 2nd 2020
Pre-project Inspections – Thursday April 9th & Friday April 10th 2020
Preparatory Letters To Owners and Resident – The Week of April 13th 2020
Town Hall Meeting – Monday May 4th 6:30pm 2020
’06 Kitchens from the 30th to 55th Floors
Work Begins Monday September 14th 2020 – Major Completion Friday October 23rd 2020
Initial Notice – The Week of July 6th 2020
Pre-project Inspections – Thursday August 6th & Friday August 7th 2020
Preparatory Letters To Owners and Resident – The Week of August 10th 2020
Town Hall Meeting – Monday August 31st 2020 6:30pm
’09 and ’10 Bathrooms from the 3rd to 29th Floors
Work Begins Monday January 4th 2021 – Major Completion Friday February 12th 2021
Initial Notice – The Week of October 19th 2020
Pre-project Inspections – Thursday November 19th & Friday November 20th 2020
Preparatory Letters To Owners and Resident – The Week of November 23rd 2020
Town Hall Meeting – Thursday December 17th 2020 6:30pm
The initial notices will include more detail, including a schedule of activities during the project, and more information regarding the inspections of each unit, which need to occur in advance of each project.
Feel free to write with any questions or concerns, parktowercondo-mgmt@habitat.com.