Events Calendar
S | M | T | W | T | F | S |
---|---|---|---|---|---|---|
1 | 2 | 4 | 7 | |||
8 | 14 | |||||
15 | 16 | 19 | 21 | |||
22 | 23 | 24 | 25 | 26 | 27 | 28 |
29 | 30 | 31 | 1 | 2 | 3 | 4 |
The contractor reported that major work is nearing completion on phase 1. A couple pours remain, but the plaza area and revolving door #1 may be back open as soon as sometime next week. And work on phase 2 is tentatively set to begin on Monday September 8th. Over the next couple months, work will continue in some places across the phase 1 locations as they button up the new surface, install the railings, and then a team will be brought in to do the masonry work. But for the most part, the plaza will be back open.
THE CIRCLE DRIVEWAY WILL BE CLOSING FOR ABOUT 6 WEEKS
Weather permitting, the driveway will be closed as the demo the sidewalk and drive surfaces, install the new waterproof membrane. Once that is in place and the contractor pours the new drive and sidewalk, it will be reopen. If we have learned anything from phase 1, it is that weather has been our worst enemy. We have lost about 6 weeks to the weather. A close second has been the unknown conditions, which we estimate we have lost about 10 working days too.
We recognize the inconvenience these projects can cause and greatly appreciate everyone’s patience and understanding while they have worked on phase 1 and transition over to phase 2. Do not hesitate to contact the office with any questions.