Replacement of the hot water riser serving the ’01 Guest Bathrooms and ‘03 Kitchens from the 3rd to 29th floors has been scheduled to begin Monday July 25th, 2016. To initiate this process, plumbing inspections of these locations are scheduled for Thursday and Friday May 19th and 20th, from 9AM to 3PM. Our plumber will take about 10 to 15 minutes per unit. We will start on the 29th floor and work down to 17 on Thursday and the 16th down to 3 on Friday.
These inspections are vital to lay the ground work for the project to begin in July. Once we have analyzed the results of the inspections, letters will go to each Owner and resident advising you what to expect and what will need to be done to prepare. In addition, we will hold an informational Town Hall Meeting on Wednesday June 29th, at 6:30PM in the Party Room. At the meeting we will describe the history and purpose of this project and details on what residents can expect including an opportunity to ask questions and address any concerns you have.
Riser replacements are among the most challenging and invasive projects needed in a building such as Park Tower. Belongings will need to be removed from the impacted locations and the water will be off every workday from 9AM to as late as 5PM while the risers are being replaced. Thankfully, to date we have replaced 13 of these risers throughout the building, so once we have completed the inspections we will be able to give you a very good picture of what to expect and how long it may take.
Work will generate some dust, be noisy at times, and there will be times you may not have use of faucets and toilets. But if you are prepared, know what to expect, and work in tandem with us, we are confident that the project will be a success.
For your convenience, below is a preliminary calendar of activities. This will be updated after the analysis of the inspection results is completed, and a detailed calendar for the project will be released before or at the Town Hall Meeting.
We thank all impacted owners and residents, including both those who live on these floors and those who live in these units, for their cooperation, patience and understanding as we plan to make these improvements.
Please contact me if you have any questions at t.patricio@dkcondo.com.
’01 Guest Bath/’03 Kitchens from 3rd to 29th Floors
INSPECTIONS
Thursday May 19th – 29th to 17th Floors
Friday May 20th – 16th to 3rd Floors
INSTRUCTION LETTER AND CALENDAR FROM MANAGEMENT
Week of Monday June 20th
TOWN HALL MEETING
Wednesday June 29th, 6:30 PM in the Party Room
TENTATIVELY EXPECT WORK TO BEGIN IN UNIT
Week of Monday July 25th – Floors 3-12
Week of Monday August 1st – Floors 14-23
Week of Monday August 8th – Floors 24-29
PLAN FOR PERIODIC WATER OUTAGES
Monday July 25th through Friday August 12th
PLAN FOR COMPLETION OF RECONSTRUCTION
Week of Monday August 15th – Floors 3-8
Week of Monday August 22nd – Floors 9-16
Week of Monday August 29th – Floors 17-22
Week of Monday September 5th – Floors 23-29