Events Calendar
S | M | T | W | T | F | S |
---|---|---|---|---|---|---|
27 | 30 | |||||
3 | 6 | 8 | ||||
10 | ||||||
17 | 18 | 20 | 21 | 22 | 23 | |
24 | 27 | 28 | 29 | 30 |
Work will be finishing up on Floors 2 and 3.
However, as many residents on some floors are aware, we found some surprises in service area conditions requiring some additional attention. The type of glue used on the old flooring requires a more challenging removal effort than expected.
Specifically Floors 15,11,9,7 and 6 are being scheduled for grinding work starting Monday September 9th through Friday September 13th. They will start at the top, 15, and work down to 6. It will be approximately one day of work per floor, give or take.
Work is expected to take place between 9am-4pm each day. The contractor will be grinding the old glue and installing the new vinyl flooring
This will be noisy at times, mostly isolated to the floors they are working on.
Work will continue over the next week on Floors 4 and 5, and barring any unknowns, Floors 2 and 3 are expected to begin Tuesday September 3rd. The scheduled work should unfold similarly to the schedule outlined below in the August 14th post.
After that, we are done with the residential hallways!
The Home Improvement Commission is working on some complementary improvements to 1P, 2P the lobby, mall and 2nd floor. This includes lighting, signage and some painting.
Also, work is pending on the budgeted improvements to the passenger elevator cabs. That is likely several months away, but a design and contract is being recommended to the Board, to be considered at a future meeting.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Hallway Remodeling Is Set To Begin On Floors 4 & 5 Monday August 19th
We Expect Floors 2 & 3 To Follow Tuesday September 3rd
Signage Is Expected To Be Installed From Floors 17 Down To 7 Next Week
After a delay for several weeks due to a supply chain issue impacting the materials used for the new signage, we’ve been told they are ready to move forward with the next 10 floors – probably some time next week.
As anticipated, the bulk of remodeling on Floors 4 and 5 will begin on Monday August 19th as scheduled. Floors 2 and 3 are expected to follow, beginning Tuesday September 3rd. Work is expected to unfold as follows:
Monday August 19th – Both floors (4 and 5) carpet removal and wall repairs and prep to begin.
Tuesday August 20th – Both floors (4 and 5) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday August 21st – Both floors (4 and 5) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday August 22nd – Both floors (4 and 5) painting continuing with walls and trim, and installation of new baseboards begins.
Friday August 23rd – Both floors (4 and 5) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday August 26th – 5th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday August 27th – 5th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday August 28th – 5th floor carpet installation. 4th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday August 29th – 4th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday August 30th – 4th floor carpet installation. Both floors (4 and 5) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Tuesday September 3rd – New light fixtures to be installed on 5th floor. Work begins on Floors 2 and 3 with carpet removal (3rd floor only) and wall prep.
Wednesday September 4th – New light fixtures to be installed on 4th floor. Work continues on Floors 2 and 3 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 4 and 5 and work will continue on 2 and 3 similar to the timeline above, albeit work on 2 will be limited to the service area at this time. Keep in mind, on days the team will be doing work to the unit doors, the doors will need to be open so the paint may be applied and have time to cure and dry properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is typically done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 6 and 7, and barring any unknowns, Floors 4 and 5 are expected to begin Monday August 19th. The scheduled work should unfold similarly to the schedule outlined below in the August 1st post.
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Floors 4 & 5 Are Anticipated To Follow Monday August 19th.
As anticipated, the bulk of remodeling on Floors 6 and 7 will begin on Monday August 5th as scheduled. Floors 4 and 5 are expected to follow, beginning Monday August 19th. Work is expected to unfold as follows:
Monday August 5th – Both floors (6 and 7) carpet removal and wall repairs and prep to begin.
Tuesday August 6th – Both floors (6 and 7) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday August 7th – Both floors (6 and 7) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday August 8th – Both floors (6 and 7) painting continuing with walls and trim, and installation of new baseboards begins.
Friday August 9th – Both floors (6 and 7) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday August 12th – 7th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday August 13th – 7th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday August 14th – 7th floor carpet installation. 6th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday August 15th – 6th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday August 16th – 6th floor carpet installation. Both floors (6 and 7) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Monday August 19th – New light fixtures to be installed on 7th floor. Work begins on Floors 4 and 5 with carpet removal.
Tuesday August 20th – New light fixtures to be installed on 6th floor. Work continues on Floors 4 and 5 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 6 and 7 and work will continue on 4 and 5 similar to the timeline above. Keep in mind, on days the team will be doing work to the unit doors, the doors will need to be open so the paint can be applied and have time to cure and dry properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is typically done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 8 and 9, and barring any unknowns, Floors 6 and 7 are expected to begin Monday August 5th. The scheduled work should unfold similarly to the schedule outlined below in the July 18th post.
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Hallway Remodeling Set To Begin On Floors 8 & 9 Monday July 22nd
Floors 6 & 7 Are Expected To Follow Monday August 5th
As anticipated, the bulk of remodeling on Floors 8 and will begin on Monday July 22nd as scheduled. Floors 6 and 7 are expected to follow, beginning Monday August 5th. Work is expected to unfold as follows:
Monday July 22nd – Both floors (8 and 9) carpet removal and wall repairs and prep to begin.
Tuesday July 23rd – Both floors (8 and 9) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday July 24th – Both floors (8 and 9) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday July 25th – Both floors (8 and 9) painting continuing with walls and trim, and installation of new baseboards begins.
Friday July 26th – Both floors (8 and 9) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday July 29th – 9th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday July 30th – 9th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday July 31st – 9th floor carpet installation. 8th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday August 1st – 8th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday August 2nd – 8th floor carpet installation. Both floors (8 and 9) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Monday August 5th – New light fixtures to be installed on 9th floor. Work begins on Floors 6 and 7 with carpet removal.
Tuesday August 6th – New light fixtures to be installed on 8th floor. Work continues on Floors 6 and 7 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 8 and 9 and work will continue on 5 and 6 similar to the timeline above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is typically done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 10 and 11, and barring any unknowns, Floors 8 and 9 are expected to begin Monday July 29th. The scheduled work should unfold similarly to the schedule outlined below in the July 3rd post.
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Hallway Remodeling Set To Begin On Floors 10 & 11 Monday July 8th
Floors 8 & 9 To Follow Monday July 22nd
As anticipated, the bulk of remodeling on Floors 10 and 11 will begin on Monday July 8th as scheduled. Floors 8 and 9 are expected to follow, beginning Monday July 22nd. Work is expected to unfold as follows:
Monday July 8th – Both floors (10 and 11) carpet removal and wall repairs and prep to begin.
Tuesday July 9th – Both floors (10 and 11) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday July 10th – Both floors (10 and 11) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday July 11th – Both floors (10 and 11) painting continuing with walls and trim, and installation of new baseboards begins.
Friday June 12th – Both floors (10 and 11) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday July 15th – 11th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday July 16th – 11th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday July 17th – 11th floor carpet installation. 10th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday July 18th – 10th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday July 19th – 10th floor carpet installation. Both floors (10 and 11) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Monday July 22nd – New light fixtures to be installed on 11th floor. Work begins on Floors 8 and 9 with carpet removal.
Tuesday July 23rd – New light fixtures to be installed on 11th floor. Work continues on Floors 8 and 9 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 10 and 11 and work will continue on 8 and 9 similar to the timeline above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is typically done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 12 and 14, and barring any unknowns, Floors 10 and 11 are expected to begin Monday July 8th. The scheduled work should unfold similarly to the schedule outlined below (June 21st post), only there will be some adjustments to allow for the July 4th holiday.
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Floors 10 and 11 are expected to follow, beginning Monday July 8th. Work is expected to unfold as follows:
Monday June 24th – Both floors (12 and 14) carpet removal and wall repairs and prep to begin.
Tuesday June 25th – Both floors (12 and 14) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday June 26th – Both floors (12 and 14) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday June 27th – Both floors (12 and 14) painting continuing with walls and trim, and installation of new baseboards begins.
Friday June 28th – Both floors (12 and 14) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday July 1st – 14th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday July 2nd – 14th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday July 3rd – 14th floor carpet installation. 12th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday July 4th – NO WORK, Independence Day Holiday
Friday July 5th – 12th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Monday July 8th – 12th floor carpet installation. Both floors (12 and 14) service area flooring and baseboards installed and touch ups throughout hallways as needed. New light fixtures to be installed on 14th floor. Work begins on Floors 11 and 12 with carpet removal.
Tuesday July 9th – New light fixtures to be installed on 12th floor. Work continues on Floors 10 and 11 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 12 and 14 and work will continue on 10 and 11 similar to the timeline above with the exception of the holiday delay. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is typically done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 15 and 16, and barring any unknowns, Floors 12 and 14 are expected to begin Monday June 24th. The scheduled work should unfold similarly to the schedule outlined below (May 23rd post), only there will be some adjustments to allow for the July 4th holidays.
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Hallway Remodeling Set To Begin On Floors 15 & 16 Monday June 10th Floors 12 & 14 To Follow Monday June 24th
As anticipated, the bulk of remodeling on Floors 15 and 16 will begin on Monday June 10th as scheduled. Floors 12 and 14 are expected to follow, beginning Monday June 24th. Work is expected to unfold as follows:
Monday June 10th – Both floors (15 and 16) carpet removal and wall repairs and prep to begin.
Tuesday June 11th – Both floors (15 and 16) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday June 12th – Both floors (15 and 16) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday June 13th – Both floors (15 and 16) painting continuing with walls and trim, and installation of new baseboards begins.
Friday June 14th – Both floors (15 and 16) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday June 17th – 16th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday June 18th – 16th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday June 19th – 16th floor carpet installation. 15th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday June 20th – 15th floor 2nd coat of paint on the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday June 21st – 15th floor carpet installation. Both floors (15 and 16) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Monday June 24th – New light fixtures to be installed on 16th floor. Work begins on Floors 12 and 14 with carpet removal.
Tuesday June 25th – New light fixtures to be installed on 15th floor. Work continues on Floors 12 and 14 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 15 and 16 and work will continue on 12 and 14 similar to the timeline above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is typically done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work is continuing and we are about ¾ of the way through the residential hallways.
Notices to all floors with specific scheduling of the work will continue to be distributed separately to each floor the week before work is expected to get underway. Barring unforeseen conditions our team expects to continue downward at a rate of two floors every two weeks. So as of now, our schedule is as follows:
Monday June 10th Floors 15 & 16
Monday June 24th Floors 12 & 14
Monday July 8th Floors 10 & 11
Monday July 22nd Floors 8 & 9
Monday August 5th Floors 6 & 7
Monday August 19th Floors 5 & 4
Friday August 30th Floors 3 & 2
Regarding the signage, due to the nature of the work and how signage is manufactured, the signage installation happens at an irregular pace. It is typically installed in batches of 5 floors at a time. So you may see remodeling done a few weeks or so prior to the new signage being put in place.
We appreciate everyone’s patience and understanding while this improvement project unfolds. If you have any questions or concerns, feel free to contact the office by e-mail at parktowercondo-mgmt@habitat.com, or call us at 773-769-3250.
Work will continue over the next week on Floors 17 and 18, and barring any unknowns, Floors 15 and 16 are expected to begin Monday June 10th. The scheduled work should unfold similarly to the schedule outlined below (May 23rd post).
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Floors 15 & 16 To Follow Monday June 10th
As anticipated, the bulk of remodeling on Floors 17 & 18 will begin on Tuesday May 28th as scheduled. Due to the Memorial Day Holiday, the team will do some wall and trim prep work on Saturday May 25th, so they can make up for some lost time. Floors 15 & 16 are expected to begin on Monday June 10th. Work is expected to unfold as follows:
Tuesday May 28th – Both floors (17 and 18) carpet removal and wall and trim preparations, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper.
Wednesday May 29th – Both floors (17 and 18) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday May 30th – Both floors (17 and 18) painting continuing with walls and trim, and installation of new baseboards begins.
Friday May 31st – Both floors (17 and 18) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday June 3rd – 18th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday June 4th – 18th floor 2nd coat of paint applied to the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday June 5th – 18th floor carpet installation. 17th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday June 6th – 17th floor 2nd coat of paint applied to the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday June 7th – 17th floor carpet installation. Both floors (17 and 18) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Monday June 10th – New light fixtures to be installed on 18th floor. Work begins on Floors 15 and 16 with carpet removal.
Wednesday June 11th – New light fixtures to be installed on 17th floor. Work continues on Floors 15 and 16 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 17 and 18 and work will continue on 15 and 16 similar to the timeline above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in the coming month with the exception of the 18th floor. This is done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed. The 18th floor is among the next batch expected to begin on June 10th.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 19 and 20, and barring any unknowns, Floors 17 and 18 are expected to begin Tuesday May 28th (following the Memorial Day holiday). The scheduled work should unfold similarly to the schedule outlined below (May 8th post).
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Floors 17 & 18 Expected To Follow On Tuesday May 28th
As anticipated, the bulk of remodeling on Floors 19 & 20 will begin on Monday May 13th as scheduled. Floors 17 & 18 are expected to begin on Tuesday May 28th (following the Memorial Day Holiday). Work is expected to unfold as follows:
Monday May 13th – Both floors (19 and 20) carpet removal and wall repairs and prep to begin.
Tuesday May 14th – Both floors (19 and 20) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday May 15th – Both floors (19 and 20) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday May 16th – Both floors (19 and 20) painting continuing with walls and trim, and installation of new baseboards begins.
Friday May 17th – Both floors (19 and 20) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday May 20th – 20th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday May 21st – 20th floor 2nd coat of paint applied to the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday May 22nd – 20th floor carpet installation. 19th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday May 23rd – 19th floor 2nd coat of paint applied to the doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday May 24th – 19th floor carpet installation. Both floors (19 and 20) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Tuesday May 28th – New light fixtures to be installed on 20th floor. Work begins on Floors 17 and 18 with carpet removal.
Wednesday May 29th – New light fixtures to be installed on 19th floor. Work continues on Floors 17 and 18 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 19 and 20 and work will continue on 17 and 18 similar to the timeline above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 21 and 22, and barring any unknowns, Floors 19 and 20 are expected to begin Monday May 13th. The scheduled work should unfold similarly to the schedule outlined below (April 26th post).
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Hallway Remodeling Is Set To Begin On Floors 21 & 22 Monday April 29th –
Floors 19 & 20 Are Expected To Follow Beginning May 13th
As anticipated, the bulk of remodeling on Floors 23 & 24 will begin on Monday April 15th as scheduled. Floors 21 & 22 are expected to begin on Monday April 29th. Work is expected to unfold as follows:
Monday April 29th – Both floors (21 and 22) carpet removal and wall repairs and prep to begin.
Tuesday April 30th – Both floors (21 and 22) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday May 1st – Both floors (21 and 22) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday May 2nd – Both floors (21 and 22) painting continuing with walls and trim, and installation of new baseboards begins.
Friday May 3rd – Both floors (21 and 22) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday May 6th – 22nd Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday May 7th – 22nd floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday May 8th – 22nd floor carpet installation. 21st floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday May 9th – 21st floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday May 10th – 21st floor carpet installation. Both floors (21 and 22) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Monday May 13th – New light fixtures to be installed on 22nd floor. Work begins on Floors 19 and 20 with carpet removal.
Tuesday May 14th – New light fixtures to be installed on 21st floor. Work continues on Floors 19 and 20 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 21 and 22 and work will continue on 19 and 20 similar to the timeline above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 23 and 24, and barring any unknowns, Floors 21 and 22 are expected to begin Monday April 29th. The scheduled work should unfold similarly to the schedule outlined below (April 11th post).
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Work is expected to unfold as follows:
Monday April 15th – Both floors (23 and 24) carpet removal and wall repairs and prep to begin.
Tuesday April 16th – Both floors (23 and 24) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday April 17th – Both floors (23 and 24) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday April 18th – Both floors (23 and 24) painting continuing with walls and trim, and installation of new baseboards begins.
Friday April 19th – Both floors (23 and 24) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday April 22nd – 24th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday April 23rd – 24th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday April 24th – 24th floor carpet installation. 23rd floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday April 25th – 23rd floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday April 26th – 23rd floor carpet installation. Both floors (23 and 24) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Monday April 29th – New light fixtures to be installed on 24th floor. Work begins on Floors 21 and 22 with carpet removal.
Tuesday April 30th – New light fixtures to be installed on 23rd floor. Work continues on Floors 21 and 22 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 23 and 24 and work will continue on 21 and 22 similar to the timeline above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 25 and 26, and barring any unknowns, Floors 23 and 24 are expected to begin Monday April 15th. The scheduled work should unfold similarly to the schedule outlined below (March 29th post).
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Monday April 1st – Both floors (25 and 26) carpet removal and wall repairs and prep to begin.
Tuesday April 2nd – Both floors (25 and 26) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday April 3rd – Both floors (25 and 26) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday April 4th – Both floors (25 and 26) painting continuing with walls and trim, and installation of new baseboards begins.
Friday April 5th – Both floors (25 and 26) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday April 8th – 26th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday April 9th – 26th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday April 10th – 26th floor carpet installation. 25th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday April 11th – 25th floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday April 12th – 25th floor carpet installation. Both floors (25 and 26) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Monday April 15th – New light fixtures to be installed on 26th floor. Work begins on Floors 23 and 24 with carpet removal.
Tuesday April 16th – New light fixtures to be installed on 26th floor. Work continues on Floors 23 and 24 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 25 and 26 and work will continue on 23 and 24 similar to the timeline above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 27 and 28, and barring any unknowns, Floors 25 and 26 are expected to begin Monday March 18th. The scheduled work should unfold similarly to the schedule outlined below (February 28th post).
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Hallway Remodeling Set To Begin
– On Floors 27 & 28 Monday March 18th –
– Floors 25 & 26 To Follow April 1st –
As anticipated, the bulk of remodeling on Floors 27 & 38 is expected to start on Monday March 18th as scheduled. Floors 25 & 26 are expected to begin on Monday April 1st. Work is expected to unfold as follows:
Monday March 18th – Both floors (27 and 28) carpet removal and wall repairs and prep to begin.
Tuesday March 19th – Both floors (27 and 28) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday March 20th – Both floors (27 and 28) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday March 21st – Both floors (27 and 28) painting continuing with walls and trim, and installation of new baseboards begins.
Friday March 22nd – Both floors (27 and 28) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday March 25th – 28th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday March 26th – 28th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday March 27th – 28th floor carpet installation. 27th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday March 28th – 27th floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday March 29th – 27th floor carpet installation. Both floors (27 and 28) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Monday April 1st – New light fixtures to be installed on 28th floor. Work begins on Floors 25 and 26 with carpet removal.
Tuesday April 2nd – New light fixtures to be installed on 27th floor. Work continues on Floors 25 and 26 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 27 and 28 and work will continue on 25 and 26 similar to the timeline above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 29 and 30, and barring any unknowns, Floors 27 and 28 are expected to begin Monday March 18th. The scheduled work should unfold similarly to the schedule outlined below (February 28th post).
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Hallway Remodeling Set To Begin
– On Floors 29 & 30 Monday March 4th –
– Floors 27 & 28 To Follow March 18th –
As anticipated, the bulk of remodeling on Floors 29 & 30 is expected to start on Monday March 4th as scheduled. Floors 27 & 28 are expected to begin on Monday March 18th. Work is expected to unfold as follows:
Monday March 4th – Both floors (29 and 30) carpet removal and wall repairs and prep to begin.
Tuesday March 5th – Both floors (29 and 30) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday March 6th – Both floors (29 and 30) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday March 7th – Both floors (29 and 30) painting continuing with walls and trim, and installation of new baseboards begins.
Friday March 8th – Both floors (29 and 30) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday March 11th – 30th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday March 12th – 30th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday March 13th – 30th floor carpet installation. 29th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday March 14th – 29th floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday March 15th – 29th floor carpet installation. Both floors (29 and 30) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Monday March 18th – New light fixtures to be installed on 30th floor. Work begins on Floors 27 and 28 with carpet removal.
Tuesday March 19th – New light fixtures to be installed on 29th floor. Work continues on Floors 27 and 28 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 29 and 30 and work will continue on 27 and 28 similar to the timeline above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 31 and 32, and barring any unknowns, Floors 29 and 30 are expected to begin Monday March 4th. The scheduled work should unfold similarly to the schedule outlined below (February 15th post).
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
As anticipated, the bulk of remodeling on Floors 31 & 32 is expected to start on Monday February 19th as scheduled. Floors 29 & 30 will begin on Monday March 4th. Work is expected to unfold as follows:
Monday February 19th – Both floors (31 and 32) carpet removal and wall repairs and prep to begin.
Tuesday February 20th – Both floors (31 and 32) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday February 21st – Both floors (31 and 32) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday February 22nd – Both floors (31 and 32) painting continuing with walls and trim, and installation of new baseboards begins.
Friday February 23rd – Both floors (31 and 32) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday February 26th – 32nd Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday February 27th – 32nd floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday February 28th – 32nd floor carpet installation. 31st floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday February 29th – 31st floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday March 1st – 31st floor carpet installation. Both floors (31 and 32) service area flooring and baseboards installed and touch ups throughout hallways as needed.
Monday March 4th – New light fixtures to be installed on 32nd floor. Work begins on Floors 29 and 30 with carpet removal.
Tuesday March 5th – New light fixtures to be installed on 31st floor. Work continues on Floors 29 and 30 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 31 and 32 and work will continue on 29 and 30 similar to the timeline above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
The new signage will be installed in a few weeks. This is done at a pace of five floors at a time as they are manufactured, so that is planned after every five hallways are completed.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 33 and 34, and barring any unknowns, Floors 31 and 32 will begin Monday February 19th. The scheduled work should unfold similarly to the expected schedule below (February 1st post).
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Hallway Remodeling Is Expected To Begin On Floors 33 & 34 Monday February 5th, Followed By Floors 31 & 32 On February 19th
As anticipated, the bulk of remodeling on Floors 33 & 34 is expected start on Monday February 5th as scheduled. Floors 31 & 32 will begin on Monday February 19th. Work is expected to unfold as follows:
Monday February 5th – Both floors (33 and 34) carpet removal and wall repairs and prep to begin.
Tuesday February 6th – Both floors (33 and 34) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday February 7th – Both floors (33 and 34) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday February 8th – Both floors (33 and 34) painting continuing with walls and trim, and installation of new baseboards begins.
Friday February 9th – Both floors (33 and 34) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday February 12th – 34th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday February 13th – 34th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday February 14th – 34th floor carpet installation. 33rd floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday February 15th – 33rd floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday February 16th – 33rd floor carpet installation. Both floors (33 and 34) service area flooring and baseboard installed and touch ups throughout hallways as needed.
Monday February 19th – New light fixtures to be installed on 34th floor. Work begins on Floors 31 and 32 with carpet removal.
Tuesday February 20th – New light fixtures to be installed on 33rd floor. Work continues on Floors 31 and 32 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items and touch ups for Floors 33 and 34 and work will continue on 31 and 32 as described above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Work will continue over the next week on Floors 35 and 36, and barring any unknowns, Floors 33 and 34 will begin Monday February 5th. The scheduled work should unfold similarly to the expected schedule below (January 19th post).
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Now that the service area flooring removal has been coordinated on all floors, and work is finishing up on new flooring between Floors 55 and 37, Hallway Remodeling of Floors 35 and 36 is expected to begin as scheduled on Monday January 22. Beginning with these floors, service area improvements will be a part of the floor by floor process.
Notices to all floors with specific scheduling of the work will be distributed separately to each floor the week before work is expected to get underway. Barring unforeseen conditions our team expects to continue downward at a rate of two floors every two weeks. So as of now, our schedule is as follows:
Monday January 22nd Floors 35 & 36
Monday February 5th Floors 33 & 34
Monday February 19th Floors 31 & 32
Monday March 4th Floors 29 & 30
Monday March 18th Floors 27 & 28
Monday April 1st Floors 25 & 26
Monday April 15th Floors 23 & 24
Monday April 29th Floors 21 & 22
With no further interruptions work will continue thereafter at a rate of two floors every two weeks.
One side note – just due to the nature of the work and how signage is manufactured, the signage installation does happen at an irregular pace. It is typically installed in batches of 5 floors at a time. So you may see remodeling done a few weeks or so prior to the new signage being put in place.
As anticipated, the bulk of remodeling on Floors 35 & 36 is expected start on Monday January 22nd as scheduled. Floors 33 & 34 will begin on Monday February 5th. Work is expected to unfold as follows:
Monday January 22nd – Both floors (35 and 36) carpet removal and wall repairs and prep to begin.
Tuesday January 23rd – Both floors (35 and 36) wall and trim preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and baseboards will be removed.
Wednesday January 24th – Both floors (35 and 36) patching and sanding will be completed and painting of walls and trim will get underway.
Thursday January 25th – Both floors (35 and 36) painting continuing with walls and trim, and installation of new baseboards begins.
Friday January 26th – Both floors (35 and 36) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday January 29th – 36th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday January 30th – 36th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday January 31st – 36th floor carpet installation. 35th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday February 1st – 35th floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday February 2nd – 35th floor carpet installation. Both floors (35 and 36) service area flooring and baseboard installed and touch ups throughout hallways as needed.
Monday February 5th – New light fixtures to be installed on 36th floor. Work begins on Floors 33 and 34 with carpet removal.
Tuesday February 6th – New light fixtures to be installed on 35th floor. Work continues on Floors 33 and 34 with hallway prep work.
Thereafter our team will be inspecting and addressing any punchlist items for Floors 35 and 36 and work will continue on 33 and 34 as described above. Keep in mind, on days when we will be doing work to the unit doors, the doors will need to be open for the work to be done properly. A member of our staff is scheduled to be present at all times.
We appreciate everyone’s patience and understanding as we make these improvements. The goal is to improve our Owners’ and residents’ living experience. We know there will be some disruption, but have confidence everyone will appreciate the results.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
SCHEDULE UPDATE – Service Area Flooring Work
Service Area Flooring Removal Got Underway On Tuesday January 2nd, however, the contractor was delayed by unforeseen conditions.
As of Wednesday January 3rd they have only completed down to Floor 47 rather than 44. However, they expect to allocate additional labor on Thursday to catch up with the original schedule by Friday January 5th. As of now, here is the expected remaining schedule:
Thursday January 4th – Service Area Floors 46-45-44-43-42-41-40-39 and if possible 38*
Friday January 5th – Service Area Floors 38* and 37-36-35-34-33-32
Monday January 8th – Service Area Floors 31-30-29-28-27-26
Tuesday January 9th – Service Area Floors 25-24-23-22-21-20
Wednesday January 10th – Service Area Floors 19-18-17-16-15-14
Thursday January 11th – Service Area Floors 12-11-10-9-8-7
Friday January 12th – Service Area Floors 6-5-4-3-2
For Floor 38*, it is their goal to finish on Thursday, but if not it will be the first floor to go on Friday.
As originally posted, while work is underway on each floor, the service elevators 5 and 6, storage rooms and the trash chute will not be accessible. This begins with the uppermost floor as listed above around 8:30am each work day, working down about 1-2 hours per floor.
As previously expected, we anticipate the floor removal efforts will begin on Tuesday January 2nd, for the Service Areas starting with the 55th Floor and working downward floor by floor. The anticipated schedule is as follows:
FLOOR REMOVAL – Service Areas (adjacent to service elevators 5 and 6, storage rooms and the trash chute) will not be accessible starting with the 55th floor at 8:30am and working down, about 1-2 hours per floor, while this work is underway:
Tuesday January 2nd- Service Area Floors 55-54-53-52-51-50
Wednesday January 3rd – Service Area Floors 49-48-47-46-45-44
Thursday January 4th – Service Area Floors 43-42-41-40-39-38
Friday January 5th – Service Area Floors 37-36-35-34-33-32
Monday January 8th – Service Area Floors 31-30-29-28-27-26
Tuesday January 9th – Service Area Floors 25-24-23-22-21-20
Wednesday January 10th – Service Area Floors 19-18-17-16-15-14
Thursday January 11th – Service Area Floors 12-11-10-9-8-7
Friday January 12th – Service Area Floors 6-5-4-3-2
SERVICE AREA IMPROVEMENTS – Hallway Remodeling will then gear back up, starting with the installation of the new Service Area flooring and base from floors 55 down to 37. Accessibility to these Service Areas will also be limited while this work is underway:
Monday January 8th- Service Areas on Floors 55 and 54
Tuesday January 9th- Service Areas on Floors 53 and 52
Wednesday January 10th- Service Areas on Floors 51 and 50
Thursday January 11th- Service Areas on Floors 49 and 48
Friday January 12th – Service Areas on Floors 47 and 46
Monday January 15th – Service Areas on Floors 45 and 44
Tuesday January 16th – Service Areas on Floors 43 and 42
Wednesday January 17th – Service Areas on Floors 41 and 40
Thursday January 18th – Service Areas on Floors 39 and 38
Friday January 19th – Service Areas on Floor 37 and touch ups from 55-37 service areas
Hallway Remodeling of Floors 35 and 36 is then expected to begin on Monday January 22. Beginning with these floors, service area improvements will be a part of the floor by floor process. Notices with specific scheduling of the work will be distributed as we get closer to those dates. As always, visit PTCondo.com for the latest, and contact our office anytime with questions or concerns at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
First, they won’t be completely halted. During this time, the contractor will be working in the hallways they’ve already completed, from 55 down to 37. They will do some touch ups and paint the inner door jams of the elevators. This will impact elevators 3 and 4 during the workdays, starting on Monday December 18th. There will be longer wait times for these elevators from time to time as they get this done.
However, the delay is the result of our team discovering asbestos is the adhesive used on some service are flooring. As discussed at the December 11th Board of Directors Meeting, while gearing up to begin the service area flooring replacement from floors 55 down to 37, our staff stumbled across this unexpected roadblock.
While making some last minute preparations, walking the anticipated work areas and completing a close up inspection of flooring in several locations, our team suspected the adhesive on some floors may contain asbestos. They had samples professionally tested and it confirmed their suspicions, though it does not appear every single floor may be impacted.
At the Board Meeting on Monday December 11th, this was discussed as well as options for asbestos mitigation. Those included either covering the old flooring with the new flooring or having the tile and problematic material removed and handled by specialists. The removal process would be carried out consistent with City of Chicago and EPA standards. The Board agreed unanimously the best option for the long term was to have this professionally removed while we are already doing work on every floor.
The good news is this is a one time effort, but it will put the brakes on the Hallway project until mid-January. We are working out specifics and logistics now, and the specialist hired to do the mitigation already submitted the necessary documentation to the City of Chicago. Our contractor coordinating the hallway remodeling will stop at the 37th and 38th floors once they are done, and work will wait until after the New Year.
We expect it to take about 10 business days for the necessary processing with the City to go through, however, the specialists did provide a preliminary schedule assuming that goes as expected:
Tuesday January 2nd- Service Area Floors 55-54-53-52-51-50
Wednesday January 3rd – Service Area Floors 49-48-47-46-45-44
Thursday January 4th – Service Area Floors 43-42-41-40-39-38
Friday January 5th – Service Area Floors 37-36-35-34-33-32
Monday January 8th – Service Area Floors 31-30-29-28-27-26
Tuesday January 9th – Service Area Floors 25-24-23-22-21-20
Wednesday January 10th – Service Area Floors 19-18-17-16-15-14
Thursday January 11th – Service Area Floors 12-11-10-9-8-7
Friday January 12th – Service Area Floors 6-5-4-3-2
A few things about this removal process. As you can see they expect to complete 6 floors per day. There will be no dust and any odor while they are working will be very minimal if any at all. There may be noticeable noise from time to time. The service area and storage lockers will not be accessible while they are working on particular floors, and elevator 6 will be reserved for them to use each of these days, to safely remove the materials. Residents will be able to walk on the concrete immediately upon completion.
We are working now with the Hallway Remodeling team on rescheduling the Service Area work from 55 down to 37, and timing to recommence work in the hallways themselves. The next floors will be 34 and 35, and if all goes well we suspect they would begin in mid-January.
As always, feel free to share any questions you have at parktowercondo-mgmt@habitat.com.
Work will begin on floors 37 and 38 as scheduled Monday December 4th, and barring any unknowns, we expect the Service Area improvements from 55 to 37 to get underway. They will be replacing the flooring, baseboards and painting. We also expect our staff to replace the light fixtures shortly following the remodeling work. Following is the preliminary schedule:
Monday December 18th- Floors 55-54 service areas
Tuesday December 19th- Floors 53-52 service areas
Wednesday December 20th- Floors 51-50 service areas
Thursday December 21st- Floors 49-48 service areas
Friday December 22nd – Floors 47-46 service areas
Monday December 25th- Christmas Day
Tuesday December 26th Floors 43-42 service areas
Wednesday December 27th Floors 41-40 service areas
Thursday December 28th Floors 39-38 service areas
December 29th – Floor 37 and punch list
1st New Years
January 2nd Back to hallways – We expect to begin with Floors 35 and 36. As progress is made, it will now include the Service Areas as they go.
The schedule for floors 37 and 38 should unfold similarly to the expected schedule below. Unit doors will be done one floor at a time, during the second week of work, on Mondays and Tuesdays then Wednesdays and Thursdays (consistent with the schedule – see November 22nd on the update below), between 9am and 5pm. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
We anticipate the hallway remodeling work to begin as expected on floors 37 and 38 on Monday December 4th. After that, the project is expected to pause while focus turns to completing Service area improvements from 55 down to 37.
Door drops with specific schedules are expected to go out for each floor, the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Monday December 4th
Both floors (37 and 38) carpet removal and hallway wall preparations with sanding and repairs to begin.
Tuesday December 5th
Both floors (37 and 38) wall preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and repairs will continue.
Wednesday December 6th
Both floors (37 and 38) wall patching and sanding will be completed and painting of walls and trim will get underway.
Thursday December 7th
Both floors (37 and 38) painting continuing with walls and trim, and installation of new baseboards begins.
Friday December 8th
Both floors (37 and 38) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday December 11th
38th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday December 12th
38th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday December 13th
38th floor carpet installation
37th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday December 14th
37th floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday December 15th
37th floor carpet installation.
Both floors (37 and 38) touch ups.
Monday December 18th – New light fixtures to be installed on 38th floor.
Tuesday December 19th – New light fixtures to be installed on 37th floor.
Thereafter our team will be addressing any punchlist items, and we anticipate there to be some touch ups throughout both hallways (37 and 38).
We would also expect the Service Area improvements from 55 to 37 to get underway. They will be replacing the flooring, baseboards and painting. We also expect our staff to replace the light fixtures shortly following the remodeling work. Following is the preliminary schedule:
Monday December 18th- Floors 55-54 service areas
Tuesday December 19th- Floors 53-52 service areas
Wednesday December 20th- Floors 51-50 service areas
Thursday December 21st- Floors 49-48 service areas
Friday December 22nd – Floors 47-46 service areas
Monday December 25th- Christmas Day
Tuesday December 26th Floors 43-42 service areas
Wednesday December 27th Floors 41-40 service areas
Thursday December 28th Floors 39-38 service areas
December 29th – Floor 37 and punch list
1st New Years
January 2nd Back to hallways – We expect to begin with Floors 35 and 36. As progress is made, it will now include the Service Areas as they go.
Contact the office with any questions at parktowercondo-mgmt@habitat.com.
Work is beginning on floors 39 and 40, and barring any unknowns, on floors 37 and 38 on Monday December 4th. The schedules should unfold similarly to the expected schedule below. There will be no work on the Thursday and Friday of Thanksgiving (November 23rd and 24th). Unit doors will be done one floor at a time, during the second week of work, on Mondays and Tuesdays then Wednesdays and Thursdays (consistent with the schedule – see November 27th on the update below), between 9am and 5pm. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
FIRST – The team at Alphabet Shop has advised they are ready to install the new signage for floors 45-50. This is expected beginning Monday November 13th.
We expect there should be very little noise or disturbance while this is done.
They are producing the signs at a pace of 5 floors at a time, and are already in production on the next batch. We will post updates as they contact our team for scheduling the next 5 floors down.
We anticipate the hallway remodeling work to begin as expected on floors 39 and 40 on Friday November 17th, and then barring any unknowns, on 37 and 38 on Monday December 4th. The schedules are expected unfold similarly on all floors. In this case though, teams are beginning with demo on Friday, and some painting on Saturday November 25th, to help compensate for the Thanksgiving holiday.
Door drops with specific schedules are expected to go out for each floor, the week before work is expected to begin. This should be delivered for floors 39 and 40 early next week.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Friday November 17th
Both floors (39 and 40) carpet removal and preparations get underway.
Monday November 20th
Both floors (39 and 40) wall preparations get underway, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and repairs will continue.
Tuesday November 21st
Both floors (39 and 40) wall patching and sanding will be completed and painting of walls and trim will get underway.
Wednesday November 22nd
Both floors (39 and 40) painting continuing with walls and trim, and installation of new baseboards begins.
Thursday November 23rd and Friday November 24th
No work – Thanksgiving Holiday.
Saturday November 25th
Both floors (39 and 40) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday November 27th
40th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday November 28th
40thnd floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday November 29th
40th floor carpet installation
39th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday November 30th
39th floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday December 1st
39th floor carpet installation.
Both floors (39 and 40) touch ups.
Monday December 4th – New light fixtures to be installed on 40th floor. Work expected to get underway on floors 37 and 38, similar to the above schedule.
Tuesday December 5th – New light fixtures to be installed on 39th floor.
Thereafter our team will be addressing any punchlist items, and the week of December 4th we anticipate there to be some touch ups throughout both hallways (39 and 40). We would also expect by then that detailed schedules will be out for the 37th and 38th floors, and work should be getting underway similar to the above schedule on Monday December 4th.
During the 2nd week of work on each hallway, unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint. This is between 9am and 5pm.
Contact the office with any questions at parktowercondo-mgmt@habitat.com.
We anticipate work to begin on floors 41 and 42 on Monday November 6th, and barring any unknowns, on floors 39 and 40 on Monday November 20th. The schedules should unfold similarly to the expected schedule below. Though there will be no work on the Thursday and Friday of Thanksgiving (November 23rd and 24th). Unit doors will be done one floor at a time, during the second week of work, on Mondays and Tuesdays then Wednesdays and Thursdays (consistent with the schedule – see October 20th Update Below), between 9am and 5pm. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
We anticipate the hallway remodeling work to begin as expected on floors 41 and 42 on Monday November 6th, and then barring any unknowns, on 39 and 40 on Monday November 20th. The schedules are expected unfold similarly on all floors.
Door drops with specific schedules are expected to go out for each floor, the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Monday November 6th
Both floors (41 and 42) carpet removal and hallway wall preparations with sanding and repairs to begin.
Tuesday November 7th
Both floors (41 and 42) wall preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and repairs will continue.
Wednesday November 8th
Both floors (41 and 42) wall patching and sanding will be completed and painting of walls and trim will get underway.
Thursday November 9th
Both floors (41 and 42) painting continuing with walls and trim, and installation of new baseboards begins.
Friday November 10th
Both floors (41 and 42) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday November 13th
42nd Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday November 14th
42nd floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday November 15th
42nd floor carpet installation
41st floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday November 16th
41st floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday November 17th
41st floor carpet installation.
Both floors (41 and 42) touch ups.
Monday November 20th – New light fixtures to be installed on 42nd floor. Work expected to get underway on floors 39 and 40, similar to the above schedule.
Tuesday November 21st – New light fixtures to be installed on 41st floor.
Thereafter our team will be addressing any punchlist items, and the week of November 6th we anticipate there to be some touch ups throughout both hallways (41 and 42). We would also expect by then that detailed schedules will be out for the 39th and 40th floors, and work should be getting underway similar to the above schedule on Monday Monday November 20th.
During the 2nd week of work on each hallway, unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint. This is between 9am and 5pm.
Contact the office with any questions at parktowercondo-mgmt@habitat.com.
OUR TEAM GOT A LEG UP ON WORK TODAY, by beginning floor preparations already on 43 and 44 – including carpet removal. This is expected to be a one-time deviation from the schedule for just these floors. Our apologies if this caught residents off guard.
We anticipate work to begin on floors 43 and 44 on Monday October 23rd, and barring any unknowns, on floors 41 and 42 on Monday November 6th. The schedules should unfold similarly to the expected schedule below. Unit doors will be done one floor at a time, during the second week of work, on Mondays and Tuesdays then Wednesdays and Thursdays (consistent with the schedule – see October 13th Update Below), between 9am and 5pm. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
The flooring in the service areas was not schedule to be done this year, just painting. However as work got underway we inquired with the Home Improvement if they wanted to consider a new base, since that was coming off as a part of the process. This was debated and they presented a recommendation at the last meeting for the Board to considered the flooring as well. The Board agreed and the materials have been ordered. contractor will be returning to do the floor and base, and going forward they will be completing it as they complete each hall.
There are several advantages to this. The flooring in the service areas was scheduled in the Association’s Reserve Study for 2026/2027, so the dollars were being accrued already – and, it means we won’t have to come back and do a whole other round of work from top to bottom. And frankly we got a great deal. Green Tech Decorating, the team doing the work, agreed to a pretty significant discount if we did it as a part of the hallway process.
Once we have the materials, they will be returning to the hallways that were completed to get this done, and of course their workers will incorporate the effort with hallways that are underway.
We anticipate the hallway remodeling work to begin as expected on floors 43 and 44 on Monday October 23rd, and barring any unknowns, on 41 and 42 on Monday November 6th. The schedules are expected unfold similarly on all floors.
Door drops with specific schedules are expected to go out for each floor, the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Monday October 23rd
Both floors (43 and 44) carpet removal and hallway wall preparations with sanding and repairs to begin.
Tuesday October 24th
Both floors (43 and 44) wall preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and repairs will continue.
Wednesday October 25th
Both floors (43 and 44) wall patching and sanding will be completed and painting of walls and trim will get underway.
Thursday October 26th
Both floors (43 and 44) painting continuing with walls and trim, and installation of new baseboards begins.
Friday October 27th
Both floors (43 and 44) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday October 30th
44th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday October 31st
44th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday November 1st
44th floor carpet installation
43rd floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday November 2nd
43rd floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday November 3rd
43rd floor carpet installation.
Both floors (43 and 44) touch ups.
Monday November 6th – New light fixtures to be installed on 44th floor. Work expected to get underway on floors 41 and 42, similar to the above schedule.
Tuesday November 7th – New light fixtures to be installed on 43rd floor.
Thereafter our team will be addressing any punchlist items, and the week of November 6th we anticipate there to be some touch ups throughout both hallways. We would also expect by then that detailed schedules will be out for the 41st and 42nd floors, and work should be getting underway similar to the above schedule on Monday Monday November 6th.
During the 2nd week of work on each hallway, unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint. This is between 9am and 5pm.
Contact the office with any questions at parktowercondo-mgmt@habitat.com.
We anticipate work to begin on floors 45 and 46 on Monday October 9th, and barring any unknowns, on floors 43 and 44 on Monday October 23rd. The schedules should unfold similarly to the expected schedule below. Unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays (consistent with the schedule – see September 29th update below), between 9am and 5pm. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
For All Other Floors…
Schedules are posted online at www.ptcondo.com, usually a couple weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
We anticipate the hallway remodeling work to begin as expected on floors 45 and 46 on Monday October 9th, and barring any unknowns, on 43 and 44 on Monday October 23rd. The schedules are expected unfold similarly on all floors.
Door drops with specific schedules are expected to go out for each floor, the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Monday October 9th
Both floors (45 and 46) carpet removal and hallway wall preparations with sanding and repairs to begin.
Tuesday October 10th
Both floors (45 and 46) wall preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and repairs will continue.
Wednesday October 11th
Both floors (45 and 46) wall patching and sanding will be completed and painting of walls and trim will get underway.
Thursday October 12th
Both floors (45 and 46) painting continuing with walls and trim, and installation of new baseboards begins.
Friday October 13th
Both floors (45 and 46) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday October 16th
46th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday October 17th
46th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday October 18th
46th floor carpet installation
45th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday October 19th
45th floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday October 20th
45th floor carpet installation.
Both floors (45 and 46) touch ups.
Monday October 23rd – New light fixtures to be installed on 46th floor. Work expected to get underway on floors 43 and 44, similar to the above schedule.
Tuesday October 24th – New light fixtures to be installed on 45th floor.
Thereafter our team will be addressing any punchlist items, and the week of October 23rd we anticipate there to be some touch ups throughout both hallways. We would also expect by then that detailed schedules will be out for the 43rd & 44th floors, and work should be getting underway similar to the above schedule on Monday October 23rd.
The schedules for each floor should unfold similarly to the 45th and 46th Floors. Work on unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
We anticipate work to begin on floors 47 and 48 on Monday September 25th, and barring any unknowns, on 45 and 46 on Monday October 9th. The schedules should unfold similarly to the expected schedule below. Unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays (consistent with the schedule), between 9am and 5pm. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
For All Other Floors
Schedules are posted online at www.ptcondo.com, usually a few weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
We anticipate the hallway remodeling work to begin on floors 47 and 48 on Monday September 25th, and barring any unknowns, on 45 and 46 on Monday October 9th. The schedules are expected unfold similarly on all floors.
Door drops with specific schedules are expected to go out for each floor, the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Monday September 25th
Both floors (47 and 48) carpet removal and hallway wall preparations with sanding and repairs to begin.
Tuesday September 26th
Both floors (47 and 48) wall preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and repairs will continue.
Wednesday September 27th
Both floors (47 and 48) wall patching and sanding will be completed and painting of walls and trim will get underway.
Thursday September 28th
Both floors (47 and 48) painting continuing with walls and trim, and installation of new baseboards begins.
Friday September 29th
Both floors (47 and 48) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday October 2nd
48th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Tuesday October 3rd
48th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Wednesday October 4th
48th floor carpet installation
47th floor, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Thursday October 5th
47th floor sand, prime and paint Unit doors. DOORS WILL BE OPEN 9am to 5pm while this work is being done. An employee of the building will be present at all times.
Friday October 6th
47th floor carpet installation.
Monday October 9th – New light fixtures to be installed on 48th floor. Work gets underway on floors 45 and 46.
Tuesday October 10th – New light fixtures to be installed on 47th floor.
Thereafter our team will be addressing any punchlist items, and the week of October 9th we anticipate there to be some touch ups throughout both hallways. We would also expect by then that detailed schedules will be out for the 45th & 46th floors, and work should be getting underway similar to the above schedule on Monday October 9th.
The schedules for each floor should unfold similarly to the 47th and 48th Floors. Work on unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
We anticipate work to begin on floors 49 and 50 on Monday September 11th, and barring any unknowns, on 47 and 48 on Monday September 25th. The schedules should unfold similarly to the expected schedule below. Unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
For All Other Floors
Schedules are posted online at www.ptcondo.com, usually a few weeks in advance of the scheduled start date. Door drops with specific schedules are expected to go out for each floor, sometime the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
We anticipate the hallway remodeling work to begin on floors 49 and 50 on Monday September 11th, and barring any unknowns, on 47 and 48 on Monday September 25th. The schedules will unfold similarly to the 51st and 52nds Floors.
Door drops with specific schedules are expected to go out for each floor, the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
Monday September 11th
Both floors (49 and 50) carpet removal and hallway wall preparations with sanding and repairs to begin.
Tuesday September 12th
Both floors (49 and 50) wall preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and repairs will continue.
Wednesday September 13th
Both floors (49 and 50) wall patching and sanding will be completed and painting of walls and trim will get underway.
Thursday September 14th
Both floors (49 and 50) painting continuing with walls and trim, and installation new baseboards begins.
Friday September 15th
Both floors (49 and 50) complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday September 18th
50th Floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Tuesday September 19th
50th floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Wednesday September 20th
50th floor carpet installation
49th floor, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Thursday September 21st
49th floor sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Friday September 22nd
49th floor carpet installation.
Monday September 25th – New light fixtures to be installed on 50th floor.
Tuesday September 26th – New light fixtures to be installed on 49th floor.
Thereafter our team will be addressing any punchlist items, and the week of September 25th we anticipate there to be some touch ups throughout both hallways. We would also expect by then that detailed schedules will be out for the 47th & 48th floors, and work should be getting underway similar to the above schedule on Monday September 25th.
The schedules for each floor should unfold similarly to the 49th and 50th Floors. Work on unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. DOORS WILL NEED TO BE OPEN FOR THE APPROPRIATE WORK TO BE DONE, and for effective drying of the new paint.
We anticipate work to begin on floors 49 and 50 on Monday September 11th, and barring any unknowns, on 47 and 48 on Monday September 25th. The schedules will unfold similarly to the 51st and 52nds Floors, however without Labor Day. work on unit doors will be done one floor at a time, Mondays and Tuesdays then Wednesdays and Thursdays. See the schedule below for reference.
Door drops with specific schedules are expected to go out for each floor, the week before work is expected to begin.
At any time should Owners or residents have any questions or concerns, or wish to share observations while the work is underway, please do not hesitate to contact the office, at parktowercondo-mgmt@habitat.com.
As Anticipated, The Updates To Floors 54 And 53 Should Start On Monday August 14th – Details Below In the Original Post.
After that, we will be working from the 52nd floor down, until all hallways have been remodeled. The progress and activity for the 52nd and 51st floors, getting underway Monday August 28th, is expected to unfold as follows:
Monday August 28th
Both floors carpet removal and hallway wall preparations with sanding and repairs to begin.
Tuesday August 29th
Both floors wall preparations continue, remove old baseboards and light fixtures, install temporary light fixtures if needed – walls throughout hallways will be prepped for new paint and wallpaper, and repairs will continue.
Wednesday August 30th
Both floors wall patching and sanding will be completed and painting of walls and trim will get underway.
Thursday August 31st
Both floors painting continuing with walls and trim, and installation new baseboards begins.
Friday September 1st
Both floors complete painting walls and trim, install wallpaper and complete installation of baseboards.
Monday September 4th – Labor Day (no work)
Tuesday September 5th
52nd floor Sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Wednesday September 6th
52nd floor carpet installation.
52nd floor, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
51st floor sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Thursday September 7th
51st floor sand, prime and paint Unit doors. DOORS WILL BE OPEN while this work is being done. An employee of the building will be present at all times.
Friday September 8th
51nd floor carpet installation.
Monday September 11th – New light fixtures to be installed on 52nd floor.
Tuesday September 12th – New light fixtures to be installed on 51st floor.
Thereafter our team will be addressing any punchlist items, and the week of September 11th we would expect there to be some touch ups throughout both hallways. We would also expect by then schedules will be out for the 49th & 50th floors, an work should be getting underway similar to the above schedule on Monday September 11th.
Work is expected to continue after that with the 52nd and 51st Floors, Monday August 28th
Consistent with the results of the recent survey, the PTCA Home Improvement Commission chose to recommend the design of the 55th Floor. This was approved by the Board of Directors at the June 12th Board Meeting and that means there will be some changes made on 53 and 54.
Our team placed orders for materials right away. Much has already been delivered for the bulk of what we need and after coordinating with the contractors, work has been scheduled.
Below is the anticipated schedule of work and activity for the 54th and 53rd Floors. Keep in mind, this is preliminary and subject to change if any unforeseen events or conditions are encountered.
For residents of these floors during this period of time, expect workers to be coming and going, periodic noise throughout the day, some dust, some odors when there is painting and gluing, and your entry doors will be open on days when sanding, priming and painting is done. This time, there will only be a light sanding of the doors, so that the new paint will sufficiently bond with the door.
Feel free to reach out to the office with any questions you may have, at 773-769-3250 or by e-mail at parktowercondo-mgmt@habitat.com. If you aren’t already on our list, let us know you to join the Park Tower e-mail group to receive news, regular updates, announcements and notices.
Hallway Remodeling Schedule
54th and 53rd Floors
PLEASE NOTE, the following schedule is based on our present expectations and is subject to change unexpectedly. We will do our best to reach out to residents as quickly as possible should that happen.
August 14th-16th Monday-Wednesday
54th Floor painting and wallpaper.
August 17th Thursday
54th Floor Unit doors light sanding and repaint. Unit doors will be open. An employee of Park Tower will be present at all times.
August 18th, 21st & 22nd Friday, Monday & Tuesday
53rd Floor painting and wallpaper.
August 23rd Wednesday
53rd Floor Unit doors light sanding and repaint. Unit doors will be open. An employee of Park Tower will be present at all times.
August 24th & 25th Thursday and Friday
53rd and 54th Floor Carpeting alterations.