GARAGE PROJECT
Town Hall Meeting
Monday February 24th, 2020 7pm
Management will hold a presentation regarding the upcoming Garage Resurfacing Project, Monday February 24th at 7pm in the 2nd Floor Party Room, to discuss in detail the project which is expected to begin Monday March 2nd.
All such meetings take place in the Party Room unless otherwise posted.
Get meeting announcements such as this via text message!
Just text the word “PTCAnotices” to 94253.
Also, get regular updates and other business news, announcements and notices by joining the Park Tower Condo Association e-mail group. Just send a request to: parktowercondo-mgmt@habitat.com
The planned Resurfacing Project on 1P and 2P is expected to begin Monday March 2nd. This will unfold over approximately 8 months, being completed in 8 phases over that time. During each phase, repairs will be performed in a different location of the garage. Work will take about 4 weeks per phase. On 1P, work will include removing the protective membrane, performing repairs to the concrete and drains, then replacing the membrane. On 2p, work will include routing and sealing of cracks, concrete and drain repairs.
During each 4 week phase, all cars in the targeted location on 1p will need to be relocated. On 2p, all cars will need to be relocated for the first 3 days. After that, parkers on 2p will only need to relocate if more substantial concrete repairs are needed in the vicinity of the parking spot. Targeted notices will go out and our team will be in touch with these parkers to schedule relocation if needed.
Following are the planned phases and impacted parking spots:
Phase 1 – Southwest March 2nd thru March 27th
1P Spots 132-145 & T16-T23
2P Spots 132-145 & T16-T23
Phase 2 – Middle South April 6th thru May 1st
1P Spots 104-110 & 146-148
2P Spots 101-108, SW, T15, 146 & 147
Phase 3 – Central and South East May 4th thru May 29th
1P Spots T14, T15, 86-102 & 111-131
2P Spots 78-98 & 109-131
Phase 4 – Central West June 1st thru June 26th
1P Spots 1-16
2P Spots 99-100 & T1-T14
Phase 5 – Middle North and West July 6th thru July 31st
1P Spots 51-76
2P Spots 26-39 & 58-71
Phase 6 – North Wall August 3rd thru August 28th
1p Spots 21-43
2p Spots 1-24 & 72
Phase 7 – Middle North and East Sept. 8th thru Oct. 2nd
1P Spots 19, 20, 44-50 & 77-85
2P Spots 40-57 & 73-77
Phase 8 – Ramps & Drives October 5th thru October 30th
No Planned Relocations
Click Here, for a Project Reference Map for 1P
Click Here, for a Project Reference Map for 2P
We expect room to provide Valet parking for 30-35 parkers on a first come first serve basis, with priority given to 1p parkers due to the nature of the work. Otherwise, the Board has approved credits for other parkers based on the period of time you must relocate outside the building. To RSVP for a Valet spot during your phase, contact the office at parktowercondo-mgmt@habitat.com. All Self-parkers should plan extra time and caution coming and going for the duration of the project, as there will be reduced lanes for traffic, and maneuvering will require patience and diligence. Also, with more valet vehicles coming and going, more areas and lanes will be blocked more often.
This project will be discussed in greater detail, Saturday February 1st at 11am in the 2nd Floor Party Room.
Contact the office with questions, at parktowercondo-mgmt@habitat.com.