Targeted Vehicle Relocation Planned Over 8 Phases
ALSO – Phase 3 Has Been Split In Half, for safety and greater ease maneuvering around these locations.
The planned Resurfacing Project on 1P and 2P is now expected to begin Wednesday April 1st. This will unfold over approximately 8 months, being completed in 8 phases over that time. During each phase, repairs will be performed in a different location of the garage. Work will take about 4 weeks per phase. On 1P, work will include removing the protective membrane, performing repairs to the concrete and drains, then replacing the membrane. On 2p, work will include routing and sealing of cracks, concrete and drain repairs.
During each 4 week phase, all cars in the targeted location on 1p will need to be relocated. On 2p, all cars will need to be relocated for the first 3 days. After that, parkers on 2p will only need to relocate if more substantial concrete repairs are needed in the vicinity of the parking spot. Targeted notices will go out and our team will be in touch with these parkers to schedule relocation if needed.
Following are the planned REVISED phases and impacted parking spots, with the anticipated Start Date and End Date:
Phase 1 – Southwest – April 1st thru April 29th
1P Spots 132-145 & T16-T23
2P Spots 132-145 & T16-T23
Phase 2 – Middle South – May 4th thru May 29th
1P Spots 104-110 & 146-148
2P Spots 101-108, SW, T15, 146 & 147
Phase 3 –South East & Down Ramp – June 1st thru June 26th
1P Spots 111-131
2P Spots 109-131
Phase 4 – East Central & Up Ramp – July 6th thru July 31st
1P Spots T14, T15, 86-102
2P Spots 78-98, 148 & 149
Phase 5 – Central West – August 3rd thru August 28th
(previously phase 4)
1P Spots 1-16 and 149
2P Spots 99-100 & T1-T14 & 151
Phase 6 – Middle North and West – Sept. 8th thru Oct. 2nd
(previously phase 5)
1P Spots 51-76
2P Spots 26-39 & 58-71
Phase 7 – North Wall – October 5th thru October 30th
(previously phase 6)
1p Spots 21-43
2p Spots 1-24 & 72
Phase 8 – Middle North and East – Nov. 2nd thru Nov. 30th
& Main Ramp (previously phase 7 & 8)
1P Spots 19, 20, 44-50 & 77-85
2P Spots 40-57 & 73-77
We expect room to provide Valet parking for 30-35 parkers on a first come first serve basis, with priority given to 1p parkers due to the nature of the work. Otherwise, the Board has approved credits for other parkers based on the period of time you must relocate outside the building. To RSVP for a Valet spot during your phase, contact the office at parktowercondo-mgmt@habitat.com. All Self-parkers should plan extra time and caution coming and going for the duration of the project, as there will be reduced lanes for traffic, and maneuvering will require patience and diligence. Also, with more valet vehicles coming and going, more areas and lanes will be blocked more often.
WORK IS EXPECTED TO BEGIN 9am ON THE DOT – Your vehicle must be moved by 9am on the start dates noted above, and may not return until work is completed.