Despite the challenges we’ve had as the liner project was concluding, we do have progress to report! First, the locker rooms are back open for business. As we do have all new fixtures and facilities, do not hesitate to contact the office for any questions. For non-members, if you want to tour the new facility, […]
IMPORTANT NOTE: The “Post Meeting Roundup” is neither official meeting minutes, nor is it intended as a replacement of actual meeting minutes for Board Meetings. The minutes of any given meeting are typically not available until after they are reviewed and approved by the Board, which usually occurs at the next scheduled meeting. Rather, the roundup […]
Good News – we expect to be able to begin filling, heating and treating the pool next week! Barring any surprises or as of yet unknown conditions, the contractor anticipates being done with the liner installation by Tuesday. After that time, our team will do a thorough cleaning of the pool area and gutters. If […]
On Wednesday August 23rd, workers will replace the carpets in all four passenger elevators in the lobby. Work is expected to begin one elevator at a time after 9am. They expect to take less than one hour per elevator, and may be finished by lunch time. A new material is being put down; carpet tiles […]
IMPORTANT NOTE: The “Post Meeting Roundup” is neither official meeting minutes, nor is it intended as a replacement of actual meeting minutes for Board Meetings. The minutes of any given meeting are typically not available until after they are reviewed and approved by the Board, which usually occurs at the next scheduled meeting. Rather, the roundup […]
Many of our improvement and repair efforts are wrapping up, but Roof Project is right around the corner. UPDATES – Friday August 11th Improvement projects status: 1. The Planter Liner Replacement Project is in its final phase, as we work out punchlist items with the General contractor and landscaper. The landscapers began planting: Below, the staff discusses irrigation […]