Phase 1 Holding at 97% Complete… Progress continued on the ramp, planter and revolving door. And we now expect the revolving door work to be completed on Wednesday September 10th. However, after inspecting the plaza area, we are asking the contractor to address several areas of the concrete aggregate where we have concerns about the […]
Watch For Chute Closing Notices… Over the summer it became apparent there may be breaches in the chute lining. After an investigation, several locations were determined to be in need of repair and the Board authorized work to be done at a recent meeting. Since that time, the necessary parts and materials were ordered, and […]
NEWS FROM MANAGEMENT: Wishing Jacquie a fond farewell 🙁– Sadly, Assistant Manager Jacquie Smith resigned from her postion with Park Tower. She thanked the Board for the opportunity to work here the past 6 years. She will not be a complete stranger though, as she moves on to other assignments within the Management Company DK […]
Phase 1 97% Complete! Phase 2 Beginning… The contractor reported that major work is nearing completion on phase 1. A couple pours remain, but the plaza area and revolving door #1 may be back open as soon as sometime next week. And work on phase 2 is tentatively set to begin on Monday September 8th. […]
Thank you to those owners who joined us for our meeting on August 26th with the Association’s Tax Attorney. Besides paying your tax bill, reading and understanding your bill can be a real challenge too. Here are some definitions of terms on the bill to help you better understand it. PIN (Property Identification Number) – […]
As we know to well, severe weather season is still with us! Mid-day on Monday, with minutes notice we went from sunny skies to a deluge and micro-burst with near 80 mile per hour winds. Cities and high-rises are not immune to the conditions we see and hear about on the news. As a reminder, here are some pretty […]