PHASE 2 75% COMPLETE Finally, railings are being installed and concrete is being poured. A plan is in place to complete the bulk of the work by Friday December 12th. Only severe cold or wet weather would halt progress at this point. Once the pours are complete, a final inspection will be conducted by Management […]
Here is your round up of business at the November 24th meeting, and the Special Meeting of the Board to review the 2015/2016 proposed budget with the Budget and Finance Committee. PARK TOWER CONDOMINIUM ASSOCIATION BOARD OF DIRECTORS MEETING Monday November 24, 2014 at 7:30PM Party Room 2nd Floor 6:30PM: CLOSED SESSION The Board held discussion […]
PARDON OUR DUST, as our staff does annual touch ups, painting and wall repairs. For those of you who have not received a notice, our staff is working their way through the building doing minor wall and door repairs, painting and other work to try to improve the aesthetics in the hallways. This is a part of […]
Phase 2 67% Visible progress slowed this week, primarily due to the weather. The cold combined with the wind made conditions very unfavorable for work to progress. However, behind the scenes materials continue being prepped for completion. Forms for the concrete pour of the driveway are being prepped. Concrete blankets have been put out to begin […]
Phase 2 65% Complete, Masonry Tuckpointing 100% Work on the Circle Driveway continues. Fortunately all we really need is dry weather to complete the work underway, so the crispy temperatures are not holding them back. This work will continue and they expect to begin installing forms and pouring the new drive as soon as next week, […]
Phase II 52% Complete; Masonry and Tuckpointing 55% Complete Work on the driveway slowed unexpectedly this week. Testing was done on the concrete patches, and unfortunately it was not ready to accept the new membrane. The testing determines whether the concrete has adequately “cured”, which is when enough moisture has disipated. Despite near perfect weather, it was too […]