When is work expected on the remaining hot water risers? That has been a very common question recently. Typically we would provide a resident with a calendar showing the year and month we expect work to start on bathrooms and kitchens throughout each tier in the building. That schedule though is influenced by multiple variables that have been moving […]
Cleaning of 1p and 2p in the garage surfaces begins with 1p on Thursday December 11th. Now that the plaza/driveway project is winding down, seasonal maintenance of the membrane and concrete surfaces of both levels of the garage has been added to our calendar. Since this maintenance was not conducted in the Spring this year, it is […]
PHASE 2 75% COMPLETE Finally, railings are being installed and concrete is being poured. A plan is in place to complete the bulk of the work by Friday December 12th. Only severe cold or wet weather would halt progress at this point. Once the pours are complete, a final inspection will be conducted by Management […]
Here is your round up of business at the November 24th meeting, and the Special Meeting of the Board to review the 2015/2016 proposed budget with the Budget and Finance Committee. PARK TOWER CONDOMINIUM ASSOCIATION BOARD OF DIRECTORS MEETING Monday November 24, 2014 at 7:30PM Party Room 2nd Floor 6:30PM: CLOSED SESSION The Board held discussion […]
PARDON OUR DUST, as our staff does annual touch ups, painting and wall repairs. For those of you who have not received a notice, our staff is working their way through the building doing minor wall and door repairs, painting and other work to try to improve the aesthetics in the hallways. This is a part of […]
Phase 2 67% Visible progress slowed this week, primarily due to the weather. The cold combined with the wind made conditions very unfavorable for work to progress. However, behind the scenes materials continue being prepped for completion. Forms for the concrete pour of the driveway are being prepped. Concrete blankets have been put out to begin […]