Our Friends At Go Grocer Made The News – In Particular The Le Cafe Delicatessen Check it out: Go Grocer Breakfast I usually shy away of making recommendations, but I am here to tell you. The Bacon Egg and Cheese Croissant, is really really crazy good!
Management Has Been Asked Repeatedly Over The Past Several Weeks About Rumors That The Bus Stop Immediately In Front Of Park Tower, Along Northbound Sheridan Road, Is Being Removed. Four Words – Not at all true. We’ve consulted with the office of Alderman Osterman, who we understand looked into these rumors personally. We were told […]
’01/’03 Riser Work Continuing – ’10/’11 Riser Scheduled As work on the High Zone ’01/’03 Riser is turning to all reconstruction related activity over the next several weeks, plans to begin the ’10/’11 Riser have gotten underway. (Both from the 30th to 55th floors.) Initial notices were issued in July, for work on the ’10 […]
UPDATED Friday August 2nd The team with Stuart Dean reported some areas of the metal have required a bit more prep work than expected. It is taking more time than originally anticipated to prepare the metal for the new coating. Work is expected to continue Monday and Tuesday, but they’ve scheduled teams to work overnight. […]
A Resident Forum Is Scheduled For Thursday August 1st at 7pm In The Party Room The Board approved holding four Resident Forums for general discussion and Q&A with Owners AND Residents. No formal Association business will be conducted and minutes will not be taken, however, a quorum of Board Members may be present. This is […]
The Team At OTIS Elevator Has Scheduled To Conduct Safety Testing Of Our Passenger Elevators OUTAGES ARE EXPECTED! July 25th through July 31st OTIS Elevator Technicians are scheduled to perform these necessary and important annual tests for Cars 1-8 on weekdays between July 25th and the 31st. Their team plans to arrive each day on-site […]