As of Monday July 2nd, work will be continuing from the 48th floor up to the 55th floor. For the most part progress has been made as planned, so they intend to continue upward 2 days per hallway. A fiber line is being run to the main media wall in each unit (ideally where your primary cable outlet is located). Residents are welcome to be home while the work is being done. All residents will need to do, is make sure any furniture or belongings are moved on their designated installation date, so workers can access the wall where your TV is located or a location you designate as a primary media wall. Visit www.ptcondo.com for more.
1 floor every 2 working days is completed, consistent with the schedule below. They work inside 8 to 9 units on day 1, and the remainder on day 2. They need about 30 minutes, between 9am and 5pm, to complete the work in each unit. They typically work in number order, in 3 to 4 units at a time beginning with the 01, 02, 03, and 04 units between 9am and 10am. As they finish those units, move to 05, 06, 07, 08, and so on. On Day 2, they expect to complete whatever units they do not get to on Day 1, and complete connections in the hallway to the main fiber line running up the building through each storage room. HOWEVER – if you’re home day 1 and have a preference for either day, feel to let them know. They are doing everything they can to accommodate any requests.
The next several weeks of anticipated progress is as follows:
Friday and Monday June 29th and July 2nd – 48th Floor Units 4801-4815
Tuesday and Thursday July 3rd and July 5th – 9th Floor Units 4901-4915
Friday and Monday July 6th and July 9th – 50th Floor Units 5001-5015
Tuesday and Wednesday July 10th and July 11th – 51st Floor Units 5101-5115
Thursday and Friday July 12th and July 13th – 52nd Floor Units 5201-5215
Monday and Tuesday July 16th and July 17th – 53rd Floor Units 5301-5315
Wednesday and Thursday July 18th and July 19th – 54th Floor Units 5401-5415
Friday and Monday July 20th and July 23rd – 55th Floor Units 5501-5515
After July 23rd, AT&T will still be working from time to time, to finish up the main line connections, but they no longer expect to need access to units.
Please contact the office with any questions, at 773-769-3250, or via e-mail at parktowercondo@dkcondo.com.