We expect a formal notice from ASTOUND to be issued within the next week, however they’ve advised the dates available for making appointments for free equipment installation will be Wednesday October 23rd through Saturday October 26th. Instructions on making your appointment and what to be prepared for will be included in the notice.
Once we receive the notice, it will be door dropped to all ’02 and ’14 units, and this post will be updated.
After ASTOUND completes the fiber line installation and repairs the drywall, our team will follow and paint the repair location. The team will visit twice on your units scheduled date – to lay down floor protection and do a first coat in the morning hours 9am to 12’ish and then a 2nd coat in the afternoon about 1-4pm. Expect about 45 minutes each visit.
The schedule for the painting phase of the work follows:
For the ’14 Units (REVISED)
Wednesday 9/25/24 55, 54, 53, 52
Thursday 9/26/24 51, 50, 49, 48
Friday 9/27/24 47, 46, 45, 44
Monday 9/30/24 43, 42, 41, 40
Tuesday 10/1/24 39, 38, 37, 36
Wednesday 10/2/24 35, 34, 33, 32
Thursday 10/3/24 31, 30, 29, 28
Friday 10/4/24 27, 26, 25, 24
Monday 10/7/24 23, 22, 21, 20
Tuesday 10/8/24 19, 18, 17, 16
Wednesday 10/9/24 15, 14, 12, 11
Thursday 10/10/24 10, 9, 8, 7
Friday 10/11/24 6, 5, 4, 3
For the ’02 Units (REVISED 09/10)
Monday 10/14/24 55, 54, 53, 52
Tuesday 10/15/24 51, 50, 49, 48
Wednesday 10/16/24 47, 46, 45, 44
Thursday 10/17/24 43, 42, 41, 40
Friday 10/18/24 39, 38, 37, 36
Monday 10/21/24 35, 34, 33, 32
Tuesday 10/22/24 31, 30, 29, 28
Wednesday 10/23/24 27, 26, 25, 24
Thursday 10/24/24 23, 22, 21, 20
Friday 10/25/24 19, 18, 17, 16
Monday 10/28/24 15, 14, 12, 11
Tuesday 10/29/24 10, 9, 8, 7
Wednesday 10/30/24 6, 5, 4, 3
Also remember, for all ’02 and ’14 Unit residents, when preparing your space for workers remember we will need a reasonable path clear to the work location (circled on the floorplans below). In general, keeping about 6′ of clearance in all directions is reasonable. This includes the wall next to the work location and the window ledge.
HAVE QUESTIONS? Don’t wait until the last minute! Please contact the office right away at 773-769-3250 or via e-mail at parktowercondo-mgmt@habitat.com.
Astound will place PVC protection for the entire 14 and 02 tiers from the top down (floors 55-3) and begin open the wall at the work location followed by vacuuming. Below are the work locations:
For all ’02 and ’14 Units, when preparing your space for workers we will need a reasonable path clear to the work location. And, for the work locations circled on the above floorplans on making about 6′ of clearance in all directions. This includes the wall adjacent to the work location and window and HVAC convector.
Astound will begin coring on Tuesday, September 3rd and that will overlap with laying of the PVC protection, and the work area will be vacuumed.
1. Installation of PVC Carpet & Floor Protection; Create Drywall Opening; Vacuum Work Location:
Tuesday September 3rd all ’02 and ’14 units from 55th to 46th floor
Wednesday September 4th all ’02 and ’14 units from 45th to 36th floor
Thursday September 5th all ’02 and ’14 units from 35th to 26th floor
Friday September 6th all ’02 and ’14 units from 25th to 16th floor
Monday September 9th all ’02 and ’14 units from 15th to 5th floor
Tuesday September 10th all ’02 and ’14 units from 4th to 3rd floor
2. Coring And Vacuuming Work Location
Tuesday September 3rd all ’02 and ’14 units from 55th to 46th floor
Wednesday September 4th all ’02 and ’14 units from 45th to 36th floor
Thursday September 5th all ’02 and ’14 units from 35th to 26th floor
Friday September 6th all ’02 and ’14 units from 25th to 16th floor
Monday September 9th all ’02 and ’14 units from 15th to 5th floor
Tuesday September 10th all ’02 and ’14 units from 4th to 3rd floor
– Installation of Backbone Fiber (Access to ALL ’02 and ’14 ALL Floors). Astound will run backbone fiber 6 days and will need access to all the units in tier, floors 55-3, the following days:
All ’14 Units All Floors – Tuesday, September 10th, Wednesday, September 11th and Thursday, September 12th
All ’02 Units All Floors – Friday, September 13th, Monday, September 16th, Tuesday, September 17th
– Fiber Rewire, Drywall Closure, Drywall Patching, Sanding and Removing of PVC to occur per the schedule below.
1. Fiber Rewiring and Drywall Closure ’14 Units
Tuesday September 10th 55th – 46th Floors
Wednesday September 11th 45th – 32nd Floors
Thursday September 12th 31st – 18th Floors
Friday September 13th 17th – 3rd Floors
2. Fiber Rewiring and Drywall Closure ’02 Units
Monday September 16th 55th – 46th Floors
Tuesday September 17th 45th – 32nd Floors
Wednesday September 18th 31st – 18th Floors
Thursday September 19th 17th – 3rd Floors
3. Patching Drywall ’14 Units
Friday September 20th 55th – 46th Floors
Monday September 23rd 45th – 36th Floors
Tuesday September 24th 35rd – 26th Floors
Wednesday September 25th 25th – 16th Floors
Thursday September 26th 15th –3rd Floors
4. Patching Drywall ’02 Units
Monday September 30th 55th – 46th Floors
Tuesday October 1st 45th – 36th Floors
Wednesday October 2nd 35th– 26th Floors
Thursday October 3rd 25th – 16th Floors
Friday October 4th 15th –3rd Floors
5. Sanding & Removing PVC ’14 Units
Tuesday September 24th 55th – 44th Floors
Wednesday September 25th 45th – 32nd Floors
Thursday September 26th 31st– 20th Floors
Friday September 27th 19th – 7th Floors
Monday September 30th 6th –3rd Floors
6. Sanding & Removing PVC ’02 Units
Wednesday October 2nd 55th – 44th Floors
Thursday October 3rd 45th – 32nd Floors
Friday October 4th 31st– 20th Floors
Monday October 7th 19th – 7th Floors
Tuesday October 8th 6th –3rd Floors
After ASTOUND completes the fiber line installation and repairs the drywall, our team will follow and paint the repair location. The team will visit twice on your units scheduled date – to lay down floor protection and do a first coat in the morning hours 9am to 12’ish and then a 2nd coat in the afternoon about 1-4pm. Expect about 45 minutes each visit.
The schedule for this phase of the work follows:
For the ’14 Units (REVISED 09/10/24!!)
Wednesday 9/25/24 55, 54, 53, 52
Thursday 9/26/24 51, 50, 49, 48
Friday 9/27/24 47, 46, 45, 44
Monday 9/30/24 43, 42, 41, 40
Tuesday 10/1/24 39, 38, 37, 36
Wednesday 10/2/24 35, 34, 33, 32
Thursday 10/3/24 31, 30, 29, 28
Friday 10/4/24 27, 26, 25, 24
Monday 10/7/24 23, 22, 21, 20
Tuesday 10/8/24 19, 18, 17, 16
Wednesday 10/9/24 15, 14, 12, 11
Thursday 10/10/24 10, 9, 8, 7
Friday 10/11/24 6, 5, 4, 3
For the ’02 Units (REVISED 09/10/24!!)
Monday 10/14/24 55, 54, 53, 52
Tuesday 10/15/24 51, 50, 49, 48
Wednesday 10/16/24 47, 46, 45, 44
Thursday 10/17/24 43, 42, 41, 40
Friday 10/18/24 39, 38, 37, 36
Monday 10/21/24 35, 34, 33, 32
Tuesday 10/22/24 31, 30, 29, 28
Wednesday 10/23/24 27, 26, 25, 24
Thursday 10/24/24 23, 22, 21, 20
Friday 10/25/24 19, 18, 17, 16
Monday 10/28/24 15, 14, 12, 11
Tuesday 10/29/24 10, 9, 8, 7
Wednesday 10/30/24 6, 5, 4, 3
Please contact us right away with any questions, either by e-mail at parktowercondo-mgmt@habitat.com, or by phone at 773-769-3250.